⚡ Due Diligence Checklist to Establish a Power-Intensive Project

High-voltage substation for utility power due diligence

Establishing a large-scale industrial, commercial, or data Centre project requires more than just land and permits. A critical component that must be evaluated early is utility power due diligence — the technical and regulatory steps needed to ensure a timely and reliable power supply.

This blog outlines a real-world due diligence checklist for utility power supply, designed to help developers avoid costly delays and secure reliable power connections from utility boards.

🔗 Related: Due Diligence Scope of Work – Substation & Utility Board Process


✅ 1. Understand Your Power Demand

Power Demand Planning for Utility Power Due Diligence

  • Assess your peak demand requirement (in kVA or MVA).
  • Determine the voltage level required based on load:
    • 110 kV / 230 kV

✅ 2. Identifying Substations in Utility Power Due Diligence

  • Locate nearby 110 kV / 230 kV / 400 kV substations.
  • Check for spare capacity and redundant supply options (for backup reliability).
  • Identify utility board grid connectivity feasibility for your site.

For official substation capacity and grid layout data, refer to the Southern Regional Grid Map by SRPC

✅ 3. Route Feasibility for Cable Laying

Cable Route Feasibility in Power Supply Planning

  • Conduct an EHV/HT route survey from substation to site.
  • Check for:
    • Road crossings, canal zones, forest/NHAI restrictions
    • Overhead vs. Underground cable options
  • Coordinate with local authorities and the utility board for alignment approvals.

✅ 4. Application & Utility Approvals

Submit a Power Feasibility Application to your State Utility (e.g., TANGEDCO, KSEB, BESCOM).

Coordinate for:

  • 🔄 Load flow study
  • 📍 Site inspection
  • 💡 Demand sanction
  • 📄 Agreement execution
  • ⚡ Energization of supply

You can apply online for HT/EHT connections through the TANGEDCO official portal for Tamil Nadu projects.”

(For other states, replace with BESCOM, KSEB, etc.)


✅ 5. Compliance & Documentation

EHT Power Checklist

Prepare the following documents before and during the process:

  • ✔️ Land ownership / lease deed
  • ✔️ Approved site layout and electrical SLD
  • ✔️ CEIG (Electrical Inspector) safety clearance
  • ✔️ Earthing and lightning protection design
  • ✔️ Technical specs of power equipment

✅ 6. Timeline & Cost Estimation for Utility Power Planning

  • 🕒 Typical energization timeline: 16-24 months
  • 💰 Key costs to consider:
    • Application & registration fees
    • TNEB charges (EMD, meter deposit, estimate cost)
    • HT/EHT cable laying cost
    • Consumer substation & civil works
    • Bay extension at utility substation
    • Monthly demand & energy charges

✅ 7. Contingency & Risk Planning

Risk & Contingency Planning in Utility Power Projects

  • Evaluate flood risks, alternate cable routes
  • Plan for DG (diesel generator) backup until permanent power is ready
  • Consider the impact of energization delays: E.g., ₹589/kVA/month may be levied for idle sanctioned demand

🏁 Final Thoughts

Early-stage due diligence for utility power supply is essential for mission-critical projects like data centres, factories, and commercial complexes.

By using this checklist, project developers can ensure technical feasibility, financial preparedness, and timely energization — avoiding setbacks before construction begins.

👉 Explore the full technical guide:
Due Diligence Scope of Work – From Grid to Site

📘 About the Author:
Visit my About Page to learn more about my experience in electrical contracting and substation project execution.

One comment

Leave a Reply

Your email address will not be published. Required fields are marked *